Box 22, Winlaw, BC V0G 2J0 info@slocanvalleyrailtrail.ca 1-888-683-7878 (SVRT)

RAIL TRAIL WORK WEEK OF SEPT. 13TH

The week of Sept. 13th is going to be a busy one on the Slocan Valley Rail Trail.
We will begin our Tree Thinning Project which will takeup to 7 working days mainly in Passmore, Winlaw and Crescent Valley. The Trail will be closed on the days the crew are in these areas, so be prepared to alter your route. Signs will be posted daily blocking the Trail where work is taking place.
A local contractor will be opening up the canopy where larger tree branches are blocking snow from reaching the Trail, limiting our winter grooming program. They will not be cutting down larger trees, but removing the limbs overhanging the Trail and leaving the tops (or crowns) intact. They will also be thinning smaller trees near the treadpath and cutting down dangerous and leaning trees. A Bucket Truck, chipper and three person crew will be undertaking this work. Funding from the Columbia Basin Trust Trail Enhancement Fund and the Community Initiative Program is making this project possible.
In other work news, a sloughing section of the Trail north of Winlaw will be closed on Tuesday, Sept. 14th where a geo-technical study will be undertaken.

As well, the Fibre Optic Project will be continuing. This CBBC funded project will find crews working primarily north of Winlaw to the Village of Slocan, installing conduit and fibre optic cable. People will be able to get through their work areas, but please use caution.

FIBRE OPTIC INSTALL UPDATE

NOTICE OF WORK: August 23-27, 2021

There will be several crews working at various locations of the Rail Trail in the weeks ahead. This upcoming week will be primarily from Slocan Park to Nixon Rd.
Crews and equipment will be installing conduits, cable vaults and fibre. Others will be doing ‘spot work’, to finish up conduit interconnects and vaults.
The section from Lemon Creek to Gravel Pit Road will not begin to have the conduit laid until early September.
Just so everyone is aware, the various stages of this Fibre Optic Project could be going on into October.
Thanks for your patience and understanding. Enjoy the Trail!

SLOCAN VALLEY RAIL TRAIL – PARTIAL CLOSURE DUE TO WILDFIRES UPDATED JULY 29TH

NOTICE OF TRAIL CLOSURE – UPDATED – July 29th Just for clarification, the Slocan Valley Rail Trail remains closed on the section that is under evacuation alert from the Trozzo Creek Wildfire. This is from north of Katelnikoff Rd to Ringrose Creek. It was mistakenly stated that it had opened. The same status applies to all Rec Sites and Trails BC trails and sites under evacuation orders/alerts or area restrictions throughout the province. Sorry for any confusion.

NOTICE OF TRAIL CLOSURE DUE TO WILDFIRE – JULY 22, 2021

NOTICE OF TRAIL CLOSURE – Because of the Evacuation Order now in place from the Trozzo Creek Wildfire, the Rail Trail is closed to everyone between Perry’s Siding and Lindsay Rd.

FIBRE OPTIC CABLE UPDATE FOR WEEK OF JULY 19TH

FIBRE OPTIC UPDATE – The crew will be resuming cable laying the week of July 19th. They will be beginning with some work in the Village of Slocan. Tentatively they will be on the Trail by Wednesday, July 21st to lay the line from the Village of Slocan to Perrys Siding. They only work Monday the Rail Trail Monday to Friday.
Please use caution on the Trail and obey all warning signs.

FIBRE OPTIC CABLE INSTALL UPDATE FOR THE WEEK OF JUNE 21ST TO 25TH

The fibre optic crew is parked at Perrys Siding for the weekend.
Crews and equipment will be installing conduit and cable vaults in the following location:
The Slocan Valley Rail Trail from just Perrys Siding Bridge Rd, north to Lemon Creek Trailhead (approximately 5 km.
Work will move south to north ~2km per day.
Trail users are encouraged to avoid travelling along this segment and obey all posted signage.
As well, a crew will be working at various locations along the Rail Trail doing
‘Spot work’ to finish and/or clean up conduit interconnects and installing vaults and lids. This work will not be trail use impacting

Construction of the Slocan Valley Fibre Optic Backbone project is taking place this summer on the rail trail from the Playmor Junction to the Village of Slocan. The work is being performed by a direction drill and vibratory plow that will bury conduit within the rail trail corridor. Every week, on Thursday or Friday, we will post the construction schedule for the coming week and advise which sections of the trail will be impacted.

This Connecting BC project is funded by local governments, the Province of BC and Columbia Basin Trust.

Fibre Optic Backbone Project UPDATE


NOTICE OF WORK JUNE 14TH TO 18TH.
The crew ended their week at Pedro Creek and will continue on to Winlaw and points north beginning on Monday. The crew only works on the Rail Trail during the week.
Trails users are encouraged to avoid travelling in this area and to obey all posted signage.

This Connecting BC project is funded by local governments, the Province of BC and Columbia Basin Trust. The work is being done by the Columbia Basin Broadband Corporation

FIBRE OPTIC LINE INSTALL UPDATE -SLOCAN VALLEY RAIL TRAIL

NOTICE OF WORK: Week of May 25
Crews and equipment will be installing conduit and cable vaults in the following locations:
The Slocan Valley Rail Trail junction at Slocan Rd South Trail and Harold Street (approximately 200m work zone)
The paved portion of the Slocan Valley Rail Trail between South Slocan Village Road and Frog Peak Café (approximately 4km work zone)
Trails users are encouraged to avoid travelling in these areas and should obey all posted signage. No work will be occurring over the long weekend.
Construction of the Slocan Valley Fibre Optic Backbone project is taking place this summer on the rail trail from the Playmor Junction to the Village of Slocan. The work is being performed by a direction drill and vibratory plow that will bury conduit within the rail trail corridor. Every Friday the contractor will be providing us with a post on the construction schedule for the coming week and advise which sections of the trail will be impacted.

This Connecting BC project is funded by local governments, the Province of BC and Columbia Basin Trust.

FIBRE-OPTIC LINE ALONG RAIL TRAIL UPDATE

MAY 13TH UPDATE – Do you have a waterline, cable or other piping that goes under the Slocan Valley Rail Trail? The Columbia Basin Broadband Corp. will be beginning the process of laying the fibre-optic line along the Rail Trail shortly.
Right now they are trying to identify all the locations where they potentially may come across a line. They will be digging a narrow trench 18″ deep. Most lines are deeper than that and it won’t be an issue. They will be reaching out to adjoining landowners, but we want to make sure no one is missed and that there are no surprises for anyone! If you think you fall into this category, please PM us. Do NOT post your details on this post, thanks.
The process of cable installation may take up to two months. Initially they may be hopping all over the place, prepping sites to link cable segment before they drop in the line.
We are hoping disruption will be minimal, but there may be brief periods when the Trail will be closed to traffic.
We will be trying our best to keep this FB page and our website up to date. Thanks for your understanding

Culvert Repair week of April 6th

WORK ON THE RAIL TRAIL – Starting Tuesday, April 6th,we’ll be repairing the culvert just north of Lemon Creek. This may take three days to complete. The Trail will be closed for part of the time. Watch for signs please.