Fibre Optic Backbone Project UPDATE

NOTICE OF WORK JUNE 14TH TO 18TH.The crew ended their week at Pedro Creek and will continue on to Winlaw and points north beginning on Monday. The crew only works on the Rail Trail during the week.Trails users… Read More

FIBRE OPTIC LINE INSTALL UPDATE -SLOCAN VALLEY RAIL TRAIL

NOTICE OF WORK: Week of May 25Crews and equipment will be installing conduit and cable vaults in the following locations:The Slocan Valley Rail Trail junction at Slocan Rd South Trail and Harold Street (approximately 200m work zone)The paved… Read More

FIBRE-OPTIC LINE ALONG RAIL TRAIL UPDATE

MAY 13TH UPDATE – Do you have a waterline, cable or other piping that goes under the Slocan Valley Rail Trail? The Columbia Basin Broadband Corp. will be beginning the process of laying the fibre-optic line along the… Read More

Culvert Repair week of April 6th

WORK ON THE RAIL TRAIL – Starting Tuesday, April 6th,we’ll be repairing the culvert just north of Lemon Creek. This may take three days to complete. The Trail will be closed for part of the time. Watch for… Read More

Support needed for Rail Trail Project

It’s that time of the year again when we ask for your support for a project we hope to do on the Slocan Valley Rail Trail. Click on this link to the Community Initiative Program of the Columbia… Read More

WORK ON THE RAIL TRAIL WEEK OF MARCH 21ST

WORK ON THE RAIL TRAIL – WEEK OF MARCH 21ST – We will be doing a culvert repair south of Slocan Park on Monday or Tuesday. A second repair will be happening north of Lemon Creek between Wednesday… Read More

Tree marking on Rail Trail explained

You may have noticed that orange dots and flagging tape have shown up at four locations along the Slocan Valley Rail Trail. It’s that time again when the trees alongside the tread path are getting overgrown and need… Read More

Art on The Trail

Art on the Rails! – The work of 20 Slocan Valley artists has now been installed along the Slocan Valley Rail Trail, just in time for Valentine’s Day. The artwork has been place close to Crescent Valley, Passmore,… Read More

Winter 2020/2021 Update

December 2, 2020 – We’re just waiting for the snow to arrive so we can start grooming the Rail Trail for all those skiers, snowshoers and walkers out there. We update our Trail Conditions page to let folks… Read More

TRAIL RESURFACING

AUGUST 29TH – In the past week, we’ve resurfaced two short segments of the Trail north of Winlaw as well as rebuilt our Lemon Creek parking lot. While the material seems soft, what it is lacking is moisture… Read More